FTSE 100 +0.64%
Pound/Dollar -0.32%
Brent Crude Oil +0.06%
Cocoa +0.06%
Euro/Dollar -0.05%

News Central

AR: Akufo-Addo commissions 330kv Kumasi-Bolgatanga power transmission project

By : cd on 18 Oct 2022, 08:59     |     Source: christian ahorgah

Pokuase Power station ECG

The President Nana Akufo Addo has inaugurated a 330 kilovolt Kumasi to Bolgatanga Transmission Line Project.

The commissioning was done on Sunday at the commencement of his four-day tour of the Ashanti Region.

The project, which is an integral part of the West Africa Power Pool Project, seeks to reinforce the Ghana Transmission System, and ensure the export of at least 100 megawatts of electricity to Burkina Faso, as well as increase the reliability of the Ghana to Burkina Interconnection Project.

To help achieve this objective, GRIDCo also constructed a 330kV Transmission line from the Aboadze Power Generation enclave through Prestea to Kumasi.

The 330 kV Kumasi-Bolgatanga Transmission Line Project consisted of the construction of approximately 550km of 330kV Transmission Line from Kumasi to Bolgatanga, the construction of 330kV Substations at Kumasi, Kintampo, Tamale and Bolgatanga as well as expansions of the existing 161kV Substations at these locations, and the implementation of Environmental Mitigation Measures and a Resettlement Action Plan for the Project.

The Project was financed by the French Development Agency (AFD) at a total cost of US$173.9 million.

Not only has the project succeeded in supplying 150 megawatts of power to Burkina Faso, but it has also increased transmission capacity to meet growing demand in Ashanti, northern Ghana and beyond.

The Minister for Energy, Matthew Opoku Prempeh, also noted that the projects have also contributed to the reduction of transmission line overloads and associated high transmission losses and improved voltages particularly in Ashanti, Bono and Bono East regions.

He stressed that the 330kV transmission lines have also helped to improve the quality and reliability of electricity supply in the country.