FTSE 100 +0.64%
Pound/Dollar -0.32%
Brent Crude Oil +0.06%
Cocoa +0.06%
Euro/Dollar -0.05%

Stories

Tamale-Daboya road set to be completed in November 2023

By : cd on 08 Aug 2021, 08:56     |     Source: christian ahorgah

Ongoing road construction

President Nana Akufo Addo has  inspected ongoing work on the two-tier Tamale Interchange, as part of his 2-day tour of the Northern Region.

According to the Director of the Department of Urban Roads, Alhaji Abass Awolu, who took President Akufo-Addo on a tour of the project, the Tamale interchange, which is a two-tier interchange, with a total length of 1 kilometre bridge and ramps, and 5 kilometres of ancillary road works, is 80% complete.

The interchange, the Director of Urban Roads said, has 19 spans, out of which these 13 spans and the ramps have all been completed, with work currently ongoing on the next six spans.

The six spans are expected to be completed in the next three months, with ancillary works, mainly asphalting, street lighting and road safety works, all to be completed before the end of 2021.

In assuring the President of the completion of the project before the end of the year, Alhaji Awolu noted that the contractor, M/S SinoHydro, is using two teams to undertake the works, with one team working from the Dakpema’s Palace section, and the other working from the Bolgatanga road section.

The Tamale Interchange is an integral part of comprehensive measures put in place by the Akufo-Addo Government to address the issues of congestion in urban centres, and to help improve travel times on major arterial roads.

Other interchanges being constructed include the PTC Roundabout Interchange in Takoradi, the Nungua Interchange which is part of the La Beach Road Completion Project, the Adjringanor Overpass, where ongoing works will be completed by the first quarter of 2022; and Phase II of the Tema Motorway Interchange.

The Tema Steelworks Road, the only concrete road to be constructed by Government since the Accra-Tema Motorway, has also been completed. Similar works are also being undertaken within the Tema Industrial enclave.

The Legon/Adjringanor roads, aimed at improving travel times within that corridor, are fifty-two percent (52%) complete; the Kumasi Roads and Drainage Extension Project, which includes the dualization of the Lake Road and lining of the Sissai River Drain in Kumasi, is seventy-five percent (75%) complete; and the Teshie Link Road, popularly referred to as the LEKMA Road, is ninety percent (90%) complete.

Tamale Asphaltic Overlay

President Akufo-Addo also inspected ongoing work on asphaltic overlays on sections of the road network in Tamale, in the Northern Region.

The contract, being undertaken by M/S Queroz Galvao Konstruktion, will see the construction of 100 kilometres of roads within the Northern, North East and Savannah Regions. Work commenced in March 2021, and expected to be completed by September 2022.

18 kilometres out of the 40-kilometre road network in the Tamale Metropolis has seen the overlay of asphalt, with construction of the remaining 22 kilometres underway. 15 kilometres of town roads in Yendi will also have the construction of asphaltic overlays over them.

Tamale-Daboya Road

President Akufo-Addo also inspected ongoing work on the upgrading of the 30.2km stretch of the Tamale-Daboya road, specifically the Tali to Daboya from a gravel surface to a bituminous surface treated road.

The works include earthworks to embank the road in low lying areas, construction of drainage structures to ensure that the road is effectively drained and, therefore, does not fail prematurely, paving and surfacing works.

The contract for implementation of the works was awarded to Messrs Maripoma Enterprise Ltd, at the cost of GHȼ119,657,337.41 for completion in thirty-six (36) calendar months. The works commenced on 16th November 2020 and is scheduled for completion by 16th November 2023

When completed, the project will reduce significantly vehicle operating cost, travel time and accidents. The project, together with the upcoming Daboya bridge project, would significantly reduce travel time between major towns in the Savannah and Northern Regions.

It will also improve access to socioeconomic facilities such as markets, schools, clinics etc. which invariably will translate into higher standard of living of the people living in communities along the project corridor.